Sewer & Water Group 761 (CC)
 
General Information
B00080
8,867 LF of sewer main replacement and 4,077 LF of water main replacement
Bose, Sheila
Post Construction
 
Construction Schedule
March 2013
May 2015
 
Cost
$1,597,000
 
Website Comments
None
 
07/01/2015
The cost and schedule data shown here are the City’s current best estimate and subject to change. Changes (if any) are updated once a month.