|
|
Project Information Details
Sewer and AC Water Group 807 (S)
(Design Bid Build Project)
|
|
Project Information Details
|
Sewer and AC Water Group 807 (S)
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B00403
(Sewer Asset)
|
Sewer and AC Water group 807 project consist of replacement of approximately 10,225 Linear Feet (LF) of sewer mains, rehabilitation of approximately 863 LF of sewer mains, and replacement of approximately 13,545 LF of water mains. The Project also includes the replacement of sewer laterals, water, services, manholes, and water and sewer appurtenances.
|
|
Jaro, Janice
|
|
9
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$8,356,081
|
Construction Activity
|
(1)
|
$6,694,794
|
(3)
|
Fully Funded
|
|
Burtech Pipeline, Incorporated
|
(1)
|
68 Months
|
|
|
See B21149 for Transportation Asset
Click Here
|
See B16087 for Water Asset
Click Here
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|