|
|
Project Information Details
Sewer and AC Water Group 812 (S)
(Design Bid Build Project)
|
|
Project Information Details
|
Sewer and AC Water Group 812 (S)
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B00426
(Sewer Asset)
|
This project will replace, install and rehabilitate a total of 11,545 LF (2.18 miles) of sewer mains, including existing 6" and 8" VC, CP, and PVC pipe. Work will include associated sewer laterals, manholes, replumbs, curb ramps, traffic control, etc.
|
|
Ramos-Banuelos, Jaime
|
|
1, 2
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$10,852,763
|
Construction Activity
|
(1)
|
$7,294,307
|
(3)
|
Fully Funded
|
|
Burtech Pipeline, Incorporated
|
(1)
|
46 Months
|
|
|
See B23059 for Transportation Asset
Click Here
|
See B17115 for Water Asset
Click Here
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|