Juniper Street Sidewalk
 
General Information
B00947
This project installs a total of approximately 1500 linear feet of PCC sidewalk along the North side of Juniper Street between Fenton Street and Westland Avenue, removing and replacing the guardrail, and 3 retainig walls.
Schaar, Luis
Construction
 
Construction Schedule
June 2013
June 2015
 
Cost
$1,130,000
 
Website Comments
None
 
06/01/2015
The cost and schedule data shown here are the City’s current best estimate and subject to change. Changes (if any) are updated once a month.