B11025 (Sewer Asset)
This project will repair 1,281 detoriated joints and PVC liners by installing sleeves using Creamer In-Weg Internal Joint seals at the Rose Canyon Trunk sewer 72", 54" and 60" pipe with estimated length of 4.7 miles.
Ninh, Michael
1, 2
University, Clairemont Mesa
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $9,584,394
Construction Activity
(1) $6,933,254
(3) Fully Funded
A.B. Hashmi, Inc.
(1) 34 Months
 
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 06/01/2018