Project Information Details
Caltrans Pacific Beach PPL Central (W)
(Design Bid Build Project)
Project Information Details
Caltrans Pacific Beach PPL Central (W)
(Design Bid Build Project)
Print Page
General Information
Project Identification Number:
B12110
(Water Asset)
Project Description:
This project will replace the existing water mains along West Mission Bay Drive Bridge with a new 8" and 20" water main.
Contact Person:
Rekani, Ronak
Council District(s):
2
Community Area(s):
MIDWAY-PACIFIC HIGHWAY, MISSION BAY PARK
Project Location Map:
Click Here
Estimated Project Schedule
(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
Estimated Project Dollar Amount
(1)
A. Total Project Cost:
(1)
$684,233
Construction Activity
A. Estimated Construction Contract Amount:
(1)
$454,495
B. Funding Status:
(3)
Fully Funded
C. Contractor:
Flatiron West, Inc
D. Expected Contract Duration:
(1)
62 Months
Additional Remarks
None
See B12097 for Sewer Asset
Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502
Updated As Of:
11/01/2024