Project Information Details
Lobrico Ct (615) Storm Drain
(Design Bid Build Project)
|
|
Project Information Details
|
Lobrico Ct (615) Storm Drain
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B13116
(Storm Water Drainage Asset)
|
Replace the existing earthen channel between Lisbon Street and Jamacha Road with below ground of approximately 340 linear feet of 48 inch RCP.
|
|
Narvaez, Rex
|
|
4
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$2,411,042
|
Construction Activity
|
(1)
|
$775,521
|
(3)
|
Fully Funded
|
|
Palm Engineering Construction Company, Inc.
|
(1)
|
19 Months
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|