The City of San Diego Project Information Details
Block 1M UUD (La Jolla 4)
(Job Order Contract Project)
The City of San Diego
Project Information Details
Block 1M UUD (La Jolla 4)
(Job Order Contract Project)
Print Page  
General Information
B13151 (Utility Undergrounding Asset)
The project will install street lights within the boundary of the District 1 Block 1M (La Jolla 4) Underground Utility Project for the Utilities Undergrounding Program.
Zhang, Dayue
1
LA JOLLA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $749,000
Construction Activity
(1) $518,001
(3) Fully Funded
CTE, Inc
(1) 24 Months
Additional Remarks
None
See B15094 for Utility Undergrounding Asset Click Here
See B12067 for Utility Undergrounding Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 03/01/2024