The City of San Diego Project Information Details
Morena Bl & W. Bernardo Medians
(To Be Determined Project)
The City of San Diego
Project Information Details
Morena Bl & W. Bernardo Medians
(To Be Determined Project)
Print Page  
General Information
B15015 (Transportation Asset)
This project includes replacing of existing 3-foot median with a new raised stamped concrete and a new black vinyl chain link fence on Morena Boulevard between Ashton Street and Littlefield Street; and removal of existing pylons on the north leg of West Bernardo Drive and to restripe in order to accomodate a 4-foot wide stamped concrete median.
Rekani, Ronak
5, 2
CLAIREMONT MESA, RANCHO BERNARDO
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $606,716
Construction Activity
(1) $321,655
(3) Fully Funded
To Be Selected
(1) 51 Months
Additional Remarks
None
See B22107 for Transportation Asset Click Here
See B21064 for Sewer Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 11/01/2024