Project Information Details
16-in & Larger CI WS Main Repl Grp A (W)
(Design Build Project)
|
|
Project Information Details
|
16-in & Larger CI WS Main Repl Grp A (W)
|
(Design Build Project)
|
Print Page
|
General Information
|
|
B15134
(Water Asset)
|
Construction of a total of 7,132 linear ft (LF) (1.35 miles) of water mains including associated water services, fire hydrants, curb ramps, traffic control, and other appurtenances.
|
|
Jaro, Janice
|
|
1, 3, 7, 2
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$7,227,614
|
Design-Build Activity
|
(1)
|
$6,470,330
|
(3)
|
Fully Funded
|
|
Orion Construction Corp/Balboa Construction Inc J.V.
|
(1)
|
109 Months
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|