The City of San Diego Project Information Details
North City Pure Water Facility
(Design Bid Build Project)
The City of San Diego
Project Information Details
North City Pure Water Facility
(Design Bid Build Project)
Print Page  
General Information
B15139 (Water Asset)
The North City Water Reclamation Plant (NCWRP) Expansion Early Site Work and Ozone/BAC Relocation package includes site work for the NCWRP, relocations of the demonstration plant Ozone/Biological Activated Carbon (BAC) units and mass grading and clearing at the NCPWF. This Early Site Work package allows site work and relocations to be constructed in advance of the ‘main’ NCWRP and NCPWF construction packages to save time and reduce procurement efforts.
Lotfi, Elham
6
UNIVERSITY
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $7,388,751
Construction Activity
(1) $4,482,944
(3) Fully Funded
Shimmick Construction Company, Inc.
(1) 28 Months
Additional Remarks
None
See B15142 for Water Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 11/01/2024