Project Information Details
Morena Conveyance Middle
(Design Bid Build Project)
|
|
Project Information Details
|
Morena Conveyance Middle
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B15141.3
(Sewer Asset)
|
The project consists of constructing approximately 18,400 LF of new 48-inch wastewater forcemain and 30-inch brine centrate conveyance pipeline, beginning at forcemain station 184+00 and brine centrate station 851+00 at Clairemont Dr north of Iroquois Avenue to forcemain station 368+00 and brine centrate station 1034+32 at Genesee Ave. north of Lehrer drive.
|
|
Tadros, Sameh
|
|
2
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$82,622,606
|
Construction Activity
|
(1)
|
$65,707,254
|
(3)
|
Fully Funded
|
|
Sukut Construction, Inc.
|
(1)
|
38 Months
|
|
|
See B15141.2 for Sewer Asset
Click Here
|
See B15141 for Sewer Asset
Click Here
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|