The City of San Diego Project Information Details
North City Pure Water Pipeline
(Design Bid Build Project)
The City of San Diego
Project Information Details
North City Pure Water Pipeline
(Design Bid Build Project)
Print Page  
General Information
B16035 (Water Asset)
Pure Water Pipeline will convey 32MGD of pure water from the proposed Pure Water Facility to the Miramar Reservoir. This project consists of the design and construction approximately 8 miles of 48-inch diameter welded steel pipeline and appurtenances. A new dechlorination facility will also be constructed near Miramar Reservoir. Approximately one mile Subaqueous pipeline system will distribute pure water within Miramar Reservoir through a series of duckbill diffusers throughout the reservoir.
Tadros, Sameh
6, 5
MILITARY FACILITIES, SCRIPPS MIRAMAR RANCH, UNIVERSITY, MIRA MESA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $163,084,466
Construction Activity
(1) $107,437,496
(3) Fully Funded
W. A. Rasic Construction Company, Inc.
(1) 49 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 04/01/2024