The City of San Diego Project Information Details
Sewer and AC Water Group 807 (W)
(Design Bid Build Project)
The City of San Diego
Project Information Details
Sewer and AC Water Group 807 (W)
(Design Bid Build Project)
Print Page  
General Information
B16087 (Water Asset)
Sewer and AC Water group 807 project consist of replacement of approximately 11,432 Linear Feet (LF) of sewer mains, rehabilitation of approximately 875 LF of sewer mains, and replacement of approximately 13,428 LF of water mains. The Project also includes the replacement of sewer laterals, water, services, manholes, and water and sewer appurtenances.
Jaro, Janice
9
COLLEGE AREA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $5,727,295
Construction Activity
(1) $4,313,591
(3) Fully Funded
Burtech Pipeline, Incorporated
(1) 68 Months
Additional Remarks
None
See B21149 for Transportation Asset Click Here
See B00403 for Sewer Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 11/01/2024