General Information
B16094 (Storm Water Drainage Asset)
The Jamacha Lomita (SD) project scope of work includes replacement of the storm drain pipes located in the easement and right-of-way with appropriately sizes RCP. The project also includes the realignments of storm drain out of the easements and into the street right-of-way. Also includes abandonment in place of existing CMP storm drain pipes and easements to be vacated as necessary. Theis project is located within the Jamacha Lomita Community Planning Area and the CD4 - council district.
Straughn, Jayna
4
SKYLINE-PARADISE HILLS
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $5,674,303
Construction Activity
(1) $3,462,882
(3) Partially Funded
To Be Selected
(1) Duration to be determined.
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.