Project Information Details
Storm Drain Group 828
(Design Bid Build Project)
|
|
Project Information Details
|
Storm Drain Group 828
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B16155
(Storm Water Drainage Asset)
|
Several CMP storm drain pipes located within the right-of-way in this neighborhood need to be replaced because the condition of the pipes are poor. Many of these pipes are corroded and have extensive damage. The deteriorated CMP storm drain pipes to be replaced with appropriate size RCP, the pipes to be extend to the well- defined low point as necessary, and energy dissipaters to be added. The project is located in the Uptown community and the CD3 - council districts.
|
|
Sleiman, Alex
|
|
3
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$2,892,468
|
Construction Activity
|
(1)
|
$1,142,150
|
(3)
|
Partially Funded
|
|
To Be Selected
|
(1)
|
Duration to be determined.
|
|
|
See B00434 for Sewer Asset
Click Here
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|