The project involves the replacement of chillers, the three existing primary water pumps with four new pumps. It also includes the modification/expansion of the existing chilled water system enclosure walls to accommodate the new equipment and all necessary piping, mechanical, electrical, instrumentation and controls as required by the cooling water system chillers upgrades and extending the existing concrete pad (6'wide X 55'long X 1' thick) and a new sidewalk (5' wide X 78' long). No ADA.
|
|
Vitelle, Brian
|
|
6
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$4,223,836
|
Construction Activity
|
(1)
|
$2,915,727
|
(3)
|
Fully Funded
|
|
Techcom International Corp
|
(1)
|
13 Months
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|