General Information
B17012 (Utility Undergrounding Asset)
Design and installation of streetlights within the Mount Acadia Bl(Mt Alifan Dr to Mt Burnham Dr) Underground Utility Project UU621.
Zhang, Dayue
2
CLAIREMONT MESA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $448,000
Construction Activity
(1) $305,200
(3) Fully Funded
CTE, Inc
(1) 18 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.