Project Information Details
Street Reconstruction Group 1801
(Design Bid Build Project)
|
|
Project Information Details
|
Street Reconstruction Group 1801
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B17188
(Transportation Asset)
|
This project will improve Gold Coast Dr from Thanksgiving Ln to Cam Ruiz and Park Dale Ave from Northrup to Mira Mesa Bl with the following: reconstruct existing street pavement and base material, install drainage/BMP structure, concrete slabs at bus stops, install/upgrade curb ramps and cross gutters, repair sidewalk, curb and gutter, relocate existing ped-push buttons, upgrade existing crosswalks with continental crosswalks, replace existing traffic striping and signal loop detectors.
|
|
Ashrafzadeh, Mastaneh
|
|
6
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$21,409,533
|
Construction Activity
|
(1)
|
$10,435,367
|
(3)
|
Partially Funded
|
|
Tri-Group Construction & Development, Inc.
|
(1)
|
Duration to be determined.
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|