The City of San Diego Project Information Details
Sherman Heights Com Center Playground
(Job Order Contract Project)
The City of San Diego
Project Information Details
Sherman Heights Com Center Playground
(Job Order Contract Project)
Print Page  
General Information
B18006 (Parks Asset)
he project scope includes removal of existing playground equipment, picnic tables, and safety surfacing. The existing ADA ramp is to be evaluated and necessary modifications made to make the playground area accessible from the public way. Some grading may be necessary to accommodate the installation of a concrete base for the new poured in place rubberized safety surfacing.This project does not include improving accessibility from the existing adjacent buildings to the play area.
Lozano, Edgar
8
SOUTHEASTERN SAN DIEGO
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $982,471
Construction Activity
(1) $259,316
(3) Fully Funded
PUB Construction Inc.
(1) 36 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 04/01/2024