Project Information Details
Howard Ave-Village Pine to Iris Sidewalk
(Design Bid Build Project)
|
|
Project Information Details
|
Howard Ave-Village Pine to Iris Sidewalk
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B18019
(Transportation Asset)
|
This project will install new concrete sidewalk on the east side of Howard Avenue between Iris Avenue and Village Pine Drive. The project will also install new curb ramps, modify the existing traffic signal, and implement traffic striping improvements.
|
|
Rekani, Ronak
|
|
8
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$1,230,142
|
Construction Activity
|
(1)
|
$485,400
|
(3)
|
Fully Funded
|
|
Fordyce Construction, Inc.
|
(1)
|
24 Months
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|