General Information
B18034 (Airport Asset)
The project will provide upgrade and bring to code the electrical system on one of the Maintenance Hangar and assess 36 smaller hangars surrounding the main hangar located at Montgomery-Gibbs Airport. Work will include the design of the electrical grid for the main hangar as well as surrounding smaller hangars, removal of current existing electrical lines and replacement of breakers/terminals and re-wiring, installation of new AMP panels, feeders and receptacles.
Gibson, William
7
KEARNY MESA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $1,666,062
Construction Activity
(1) $681,656
(3) Fully Funded
Ace Electric, Inc.
(1) 10 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 11/01/2024