The City of San Diego Project Information Details
Pipeline Rehabilitation AU-1
(Design Bid Build Project)
The City of San Diego
Project Information Details
Pipeline Rehabilitation AU-1
(Design Bid Build Project)
Print Page  
General Information
B18037 (Sewer Asset)
This project consists of 7.18 miles. The project also includes reconnection of 770 laterlas, rehab of 5 manholes, repair of 8 manholes, replacement of 2 manholes, and installation of 7 manholes and 29 cleanouts.
Ramos-Banuelos, Jaime
7, 2
LINDA VISTA, CLAIREMONT MESA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $5,205,821
Construction Activity
(1) $3,609,409
(3) Fully Funded
Southwest Pipeline and Trenchless, Inc.
(1) 69 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.