The City of San Diego Project Information Details
AC Water & Sewer Group 1052 (S)
(Design Bid Build Project)
The City of San Diego
Project Information Details
AC Water & Sewer Group 1052 (S)
(Design Bid Build Project)
Print Page  
General Information
B18096 (Sewer Asset)
Replace 1.23 milts of existing sewer in council district 8 & 9, Southeastern San Diego and Barrio Logan community.
Jaro, Janice
8, 4
BARRIO LOGAN, SOUTHEASTERN SAN DIEGO
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $3,973,471
Construction Activity
(1) $2,796,599
(3) Fully Funded
Burtech Pipeline, Incorporated
(1) 32 Months
Additional Remarks
None
See B24092 for Transportation Asset Click Here
See B18092 for Water Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 11/01/2024