The City of San Diego Project Information Details
South Mission Beach GI
(Design Bid Build Project)
The City of San Diego
Project Information Details
South Mission Beach GI
(Design Bid Build Project)
Print Page  
General Information
B18118 (Storm Water Drainage Asset)
INSTALLATION OF STORM DRAIN, BIOFILTRATION AND INFILTRATION BASINS, LOW FLOW DIVERSION STRUCTURES, AND STREET RESURFACING THROUGHOUT VARIOUS SECTIONS OF SOUTH MISSION BEACH INCLUDING MISSION BOULEVARD, SAN FERNANDO PLACE, SAN GABRIEL PLACE, CAPISTRANO PLACE, COHASSET COURT, AND BALBOA COURT. CONSTRUCTION CONSISTS OF STORM DRAIN LATERALS THROUGH THE ALLEY SECTIONS ALONG MISSION BOULEVARD. THE PIPE SIZE INSTALLATION WILL RANGE FROM 48 INCHES, 36 INCHES, 30 INCHES, 24 INCHES, 18 INCHES, AND 15 INCH
Lotfi, Elham
2
MISSION BAY PARK, MISSION BEACH
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $11,482,560
Construction Activity
(1) $7,519,629
(3) Partially Funded
To Be Selected
(1) Duration to be determined.
Additional Remarks
None
See B23088 for Transportation Asset Click Here
See B18117 for Storm Water Drainage Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 03/01/2024