The City of San Diego Project Information Details
Accelerated Sewer Referral Group 847
(Design Bid Build Project)
The City of San Diego
Project Information Details
Accelerated Sewer Referral Group 847
(Design Bid Build Project)
Print Page  
General Information
B18183 (Sewer Asset)
The project consists of replacing approximately 0.38 miles of
existing 6 ¿replaced with 8-inch¿ and 8-inch vitrified clay, cast iron, concrete and polyvinyl chloride sewer mains. Replacement segments located outside of the right of way, which require additional easement acquisition. Replacement is proposed for all service laterals that connect to the sewer main. New cleanouts will be installed at the property line for any laterals that do not already have existing cleanouts.
Narvaez, Rex
1, 3, 7, 9, 2, 4
LA JOLLA, DOWNTOWN, GREATER GOLDEN HILL, LINDA VISTA, MIDWAY-PACIFIC HIGHWAY, PACIFIC BEACH, ENCANTO NEIGHBORHOODS, SOUTHEASTERN SAN DIEGO
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $2,028,300
Construction Activity
(1) $1,242,900
(3) Partially Funded
To be selected
(1) Duration to be determined.
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 04/01/2024