The City of San Diego
Project Information Details
Regional Arterial Guardrail Group 2a
(Job Order Contract Project)
Print Page  
General Information
B18201 (Transportation Asset)
The project scope includes installation of guardrail, sidewalk, curb extension, and curb ramp along Black Mountain Road from the intersection with Park Village Road/Adolphia Street.
Zhang, Dayue
5
RANCHO PENASQUITOS
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $587,850
Construction Activity
(1) $260,032
(3) Fully Funded
Ramona Paving, Inc
(1) 14 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.