The City of San Diego Project Information Details
PIPELINE REHABILITATION AX-1
(Design Bid Build Project)
The City of San Diego
Project Information Details
PIPELINE REHABILITATION AX-1
(Design Bid Build Project)
Print Page  
General Information
B18203 (Sewer Asset)
The proposed scope of work consists of trench-less rehabilitation of approximately 27,846 LF (5.27miles) of existing 8-inch and 12-inch vitrified clay pipe (VCP) sewer mains. The project also includes approximately 7 point repairs, rehabilitation of all associated sewer laterals from sewer main to property line, rehabilitation of 40 manholes, replacement of 6 manholes, repair of 6 manholes, installation of 10 new main line cleanouts.
Ramos-Banuelos, Jaime
4
ENCANTO NEIGHBORHOODS
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $4,336,400
Construction Activity
(1) $2,833,219
(3) Fully Funded
Southwest Pipeline and Trenchless, Inc.
(1) 53 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 11/01/2024