|
|
Project Information Details
Pipeline Rehabilitation AY-1
(Design Bid Build Project)
|
|
Project Information Details
|
Pipeline Rehabilitation AY-1
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B18212
(Sewer Asset)
|
Rehabilitation of approximately 40,623 L.F. (7.69 miles) of existing 8-inch and 10-inch vitrified clay pipe (V.C.P) sewer mains. The project also includes point repairs, rehabilitation of sewer laterals and installation of sewer lateral clean outs at property line, rehabilitation of manholes, replacement of manholes, repair of manholes, installation of clean outs and manholes.
|
|
Ramos-Banuelos, Jaime
|
|
1, 7, 2
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$5,748,420
|
Construction Activity
|
(1)
|
$4,213,104
|
(3)
|
Fully Funded
|
|
Burtech Pipeline, Incorporated
|
(1)
|
42 Months
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|