Project Information Details
Santa Clara Playground Improvements
(Design Bid Build Project)
|
|
Project Information Details
|
Santa Clara Playground Improvements
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B19029
(Parks Asset)
|
This existing playground footprint is approximately 5,400 square feet. It is not necessary for the playground design to stay within the existing play area footprint. The playground should be designed to include play areas for various age groups. Picnic facilities and shade shelters could be included in the design to accommodate group gatherings such as birthday parties if space permits. The path of travel from the parking lot to the comfort station appears to be compliant with today’s access
|
|
Lozano, Edgar
|
|
2
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$1,829,500
|
Construction Activity
|
(1)
|
$858,071
|
(3)
|
Fully Funded
|
|
Marcon Engineering Inc
|
(1)
|
17 Months
|
|
|
See B19032 for Parks Asset
Click Here
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|