The City of San Diego Project Information Details
Rancho Penasquitos Improv 1(W)
(Design Build Project)
The City of San Diego
Project Information Details
Rancho Penasquitos Improv 1(W)
(Design Build Project)
Print Page  
General Information
B19093 (Water Asset)
Replace approximately 2,899 linear feet ¿LF¿ ¿0.55 miles¿ of existing 8, 10 and 12 inch diameter asbestos cement ¿AC¿ distribution/transmission mains with Polyvinyl Chloride ¿PVC¿ including associated water
services, valves, fire hydrants, curb ramps, traffic control, etc. Add new water mains of approximately 2,473 ¿LF¿ ¿0.47 miles¿ Polyvinyl Chloride ¿PVC¿. Abandon/remove existing water mains surrounding the
Los Penasquitos pump station and the pump station itself.
Sleiman, Alex
5
CARMEL MOUNTAIN RANCH, RANCHO PENASQUITOS
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $7,221,257
Design-Build Activity
(1) $5,941,378
(3) Fully Funded
TC Construction Co., Inc.
(1) 49 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 04/01/2024