|
|
Project Information Details
Bay Ho Improv 2 (W)
(Design Bid Build Project)
|
|
Project Information Details
|
Bay Ho Improv 2 (W)
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B19106
(Water Asset)
|
Replace approximately 7,543 linear feet (1.43 mi) of 4-, 6-, 8-, and 12-inch existing AC Mains with new appropriately sized PVC water Mains.
|
|
Ramos-Banuelos, Jaime
|
|
2
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$7,463,252
|
Construction Activity
|
(1)
|
$4,400,008
|
(3)
|
Fully Funded
|
|
SC VAlley Engineering, Inc.
|
(1)
|
44 Months
|
|
|
See B25012 for Transportation Asset
Click Here
|
See B19104 for Sewer Asset
Click Here
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|