|
|
Project Information Details
Redwood Village/Rolando Park Improv 1(S)
(Design Bid Build Project)
|
|
Project Information Details
|
Redwood Village/Rolando Park Improv 1(S)
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B19139
(Sewer Asset)
|
Construction of approximately 9,129 linear feet (1.73 miles) of polyvinyl chloride (PVC) sewer mains to replace existing 6, 8 and 10-inch diameter vitrified clay (VC), PVC, and asbestos cement (AC) sewer mains, via open trench and trenchless methods, including associated laterals, manholes, cleanouts, and other appurtenances.
|
|
Ramos-Banuelos, Jaime
|
|
9
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$10,239,351
|
Construction Activity
|
(1)
|
$6,408,592
|
(3)
|
Partially Funded
|
|
TC Construction Co., Inc.
|
(1)
|
Duration to be determined.
|
|
|
See B19141 for Water Asset
Click Here
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|