|
|
Project Information Details
AC Water and Sewer Group 1052A (W)
(Design Build Project)
|
|
Project Information Details
|
AC Water and Sewer Group 1052A (W)
|
(Design Build Project)
|
Print Page
|
General Information
|
|
B19166
(Water Asset)
|
Replacement of approx 9,473 (LF) (1.8 miles) of existing 4, 6, 8, 12 and 16” diameter asbestos cement (AC) distribution mains with Polyvinyl Chloride (PVC) pipes. Abandon 1,878 LF (0.36 miles) of 4, 6, 12 and 16” AC Water mains, Construct approx 493 LF (0.093 miles) of new water pipes including associated water services, fire hydrants, air valves, blowoff, high lining, water main cut-and-plugs and reconnections and other associated work. All water main installation and surface improvements shal
|
|
Rubalcava, Eric
|
|
8, 4
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$8,040,041
|
Design-Build Activity
|
(1)
|
$6,135,041
|
(3)
|
Fully Funded
|
|
TC Construction Co., Inc.
|
(1)
|
28 Months
|
|
|
See B24059 for Transportation Asset
Click Here
|
See B19169 for Sewer Asset
Click Here
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|