Dusty Rhodes Comfort Station Improvement
(Design Bid Build Project)
|
|
Project Information Details
|
Dusty Rhodes Comfort Station Improvement
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B19180
(Parks Asset)
|
This project provides for design and construction to replace the existing comfort station, parking lot, and playground at Dusty Rhodes Park. Dusty Rhodes Comfort Station - The existing comfort station is to be replaced with a new pre-fabricated comfort station with unisex stalls.
|
|
Oliver, Kevin
|
|
2
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$2,340,334
|
Construction Activity
|
(1)
|
$1,200,000
|
(3)
|
Fully Funded
|
|
To be selected
|
(1)
|
10 Months
|
|
|
See B19158 for Parks Asset
Click Here
|
See B19181 for Parks Asset
Click Here
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|