The City of San Diego Project Information Details
Pipeline Rehabilitation BB-1
(Design Bid Build Project)
The City of San Diego
Project Information Details
Pipeline Rehabilitation BB-1
(Design Bid Build Project)
Print Page  
General Information
B19201 (Sewer Asset)
Sewer Improvements:
Rehabilitate 35,641 linear feet ¿6.75 miles¿ of existing 8-inch and 10-inch vitrified clay sewer mains including rehabilitating all associated laterals ¿approximately 926¿ from sewer main to property line,
installation of 3 manholes, replacement of 11 manholes, repair of 11 manholes, rehabilitation of 141 manholes, and installation of 31 cleanouts. The project also includes approximately 14 external point
repairs, 4 internal point repairs for intruding laterals, and 19 intern
Ramos-Banuelos, Jaime
7, 2
CLAIREMONT MESA, NAVAJO
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $5,738,200
Construction Activity
(1) $4,009,200
(3) Fully Funded
Burtech Pipeline, Incorporated
(1) 36 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 04/01/2024