The City of San Diego Project Information Details
Clairemont Mesa East Improv 3 (S)
(Design Bid Build Project)
The City of San Diego
Project Information Details
Clairemont Mesa East Improv 3 (S)
(Design Bid Build Project)
Print Page  
General Information
B20026 (Sewer Asset)
Construction of 627 linear feet ¿LF¿ ¿0.12 miles¿ of 8-inch sewer mains to replace existing vitrified clay ¿VC¿ sewer mains. Rehabilitation of approximately 5,659 LF ¿1.07 miles¿ of existing 8-inch diameter vitrified clay ¿VC¿ sewer mains. Sewer improvements also include the replacement of all associated sewer laterals, manholes, and other appurtenances.
Sleiman, Alex
2
CLAIREMONT MESA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $4,497,749
Construction Activity
(1) $2,510,332
(3) Partially Funded
KTA Construction, Inc.
(1) Duration to be determined.
Additional Remarks
None
See B20043 for Water Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 04/01/2024