Bay Terraces Improv 1 (S)
(Design Bid Build Project)
The City of San Diego
Project Information Details
Bay Terraces Improv 1 (S)
(Design Bid Build Project)
Print Page  
General Information
B20027 (Sewer Asset)
Replace approximately 2,953 LF (0.56 miles) of 8-inch vitrified clay (VC) and polyvinyl chloride (PVC), abandon 936 LF (0.18 miles) of 8-inch PVC, install 668 LF (0.13 miles) of 8-inch PVC, and rehabilitate 684 LF
(0.13 miles) of 8-inch VC sewer main, including associated sewer laterals, manholes, curb ramps, traffic control, etc. Additionally, the project proposed to replumb laterals (for easement vacation), abandon 2 manholes and install 2 new manholes (for a flow redirection), install 3 clean
Ramos-Banuelos, Jaime
4
SKYLINE-PARADISE HILLS
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $3,997,391
Construction Activity
(1) $2,801,892
(3) Partially Funded
Palm Engineering Construction Company, Inc.
(1) Duration to be determined.
Additional Remarks
None
See B20029 for Water Asset Click Here
See B24114 for Transportation Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.