The City of San Diego Project Information Details
Corridor Improv 1 (S)
(Design Build Project)
The City of San Diego
Project Information Details
Corridor Improv 1 (S)
(Design Build Project)
Print Page  
General Information
B20036 (Sewer Asset)
Construction of 5,242 LF of 8-, 10-. and 12- inch sewer mains to replace existing vitrified clay sewer mains. Construction of 530LF of new 12-inch sewer main. Rehabilitation of 3,669LF of existing VC sewer mains and abandonment of 552 LF of existing VC sewer main. Included will be the construction of 102 curb ramps and 6 alley aprons.
Narvaez, Rex
9
MID-CITY:CITY HEIGHTS
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $4,892,800
Design-Build Activity
(1) $3,699,500
(3) Fully Funded
To Be Selected
(1) 27 Months
Additional Remarks
None
See B20037 for Water Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.