General Information
B20072 (Water Asset)
This project will repair the corroded Manways at 3 locations on Kearny Mesa pipeline as a preventive action to eliminate water main break at the location of these Manways. In some locations air valve will be raised to grade level. All the work will be to the existing pipeline and appurtenant structures within the developed area.
Vitelle, Brian
1
PACIFIC BEACH
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $1,177,425
Construction Activity
(1) $568,764
(3) Fully Funded
Burtech Pipeline, Incorporated
(1) 15 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.