The City of San Diego Project Information Details
Kellogg Comfort Station Improvements
(Job Order Contract Project)
The City of San Diego
Project Information Details
Kellogg Comfort Station Improvements
(Job Order Contract Project)
Print Page  
General Information
B20120 (Parks Asset)
Scope consist of installing a trench drain to prevent water from running across the boardwalk. Extending the roof line by 3.5 ft over the proposed trench drain to comply with the latest Storm Water compliance
Lewis, Nikki
1
LA JOLLA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $267,855
Construction Activity
(1) $119,500
(3) Fully Funded
Ramona Paving, Inc
(1) 11 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 04/01/2024