B20137 (Sewer Asset)
The Point Loma Scum Concentrators are at the end of their useful life and are in need of replacement and upgrade. A study was performed to assist in determining the best course of action for replacement of the scum concentrators.
Remove existing scum concentrators and replace system with scum screens, a decanter and associated piping so that the scum can be injected into the digesters.
Vitelle, Brian
2
PENINSULA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $3,357,302
Construction Activity
(1) $2,197,700
(3) Partially Funded
To be selected
(1) Duration to be determined.
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.