The City of San Diego Project Information Details
Trench Paving Sewer & AC Water Grp 697A
(Design Bid Build Project)
The City of San Diego
Project Information Details
Trench Paving Sewer & AC Water Grp 697A
(Design Bid Build Project)
Print Page  
General Information
B21015 (Transportation Asset)
Resurfacing of streets (not suitable for a slurry seal) as a result of trench cuts caused by Public Utilities Dept (PUD) sublets for Sewer & AC Water Group 697A.
Ramos-Banuelos, Jaime
3, 8
GREATER GOLDEN HILL, SOUTHEASTERN SAN DIEGO
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $385,000
Construction Activity
(1) $385,000
(3) Fully Funded
Burtech Pipeline, Incorporated
(1) 39 Months
Additional Remarks
None
See B20079 for Storm Water Drainage Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 11/01/2024