B21054 (Water Asset)
This project is to install six (6) access doors (3' x 6') in the baffle walls of the flocculation basins 3 & 4 which would ease the mobility for maintenance personnel and safer access to different sections of the basin. Each flocculation basin needs three (3) access doors, one (1) access door for each baffle wall separating the three stage flocculation. Along with the doors, stainless steel fasteners, and other metallic hardware are required (316 SS, minimum).
Lewis, Nikki
7
NAVAJO
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $277,915
Construction Activity
(1) $100,281
(3) Fully Funded
LDCO - Luan Dauti
(1) 3 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.