General Information
B22007 (Sewer Asset)
This project includes rehabilitation of 2.64 miles of 8 & 12-inch VC sewer mains, and including associated laterals, manholes, cleanouts, and other appurtenances.
The project is located within Encanto Community (Council District 4).
Jaro, Janice
4
ENCANTO NEIGHBORHOODS, SKYLINE-PARADISE HILLS
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
If timeline does not show, please click here for instructions on how to resolve this.
?
?
Start
Preliminary
Engineering/Design
Reporting
data as of
Finish
Design
0
0
 
Estimated Project Dollar Amount(1)   
(1) $5,262,900
Construction Activity
(1) $2,792,000
(3) Partially Funded
To be selected
(1) Duration to be determined.
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.