General Information
|
|
B22011
(Sewer Asset)
|
Rehabilitation of 20,771LF existing vitrified clay ﴾VC﴿ sewer mains, 515 sewer laterals and 3 manholes. Install of 1 external and 4 internal point repairs. Installation of 20 new sewer cleanouts and 3 new sewer manholes. The project scope may also include ADA improvements pending compliance verification by the Design Team of affected existing curb ramps. No AC paving of all areas impacted by this project. This project is located in council district 4, within the Skyline – Paradise Hills communi
|
|
Jaro, Janice
|
|
4
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$3,606,936
|
Construction Activity
|
(1)
|
$2,497,426
|
(3)
|
Partially Funded
|
|
Southwest Pipeline and Trenchless, Inc.
|
(1)
|
Duration to be determined.
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|