|
|
Project Information Details
North Park Improv 2 (W)
(Design Bid Build Project)
|
|
Project Information Details
|
North Park Improv 2 (W)
|
(Design Bid Build Project)
|
Print Page
|
General Information
|
|
B22021
(Water Asset)
|
This project will replace a total of approximately 12,311 linear feet ﴾2.33 miles﴿ of 6 and 8‐inch asbestos cement ﴾AC﴿ water main with appropriately sized PVC mains per water modeling. Including all associated water services, fire hydrant, curb ramps, traffic control, street resurfacing etc. Limits of work ends at curb return and a valve to be installed at connection to existing AC water on University Avenue.
|
|
Jaro, Janice
|
|
3
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$15,841,988
|
Construction Activity
|
(1)
|
$11,835,226
|
(3)
|
Partially Funded
|
|
TC Construction Co., Inc.
|
(1)
|
Duration to be determined.
|
|
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|