The City of San Diego Project Information Details
Adams North Improv 1 (S)
(Design Build Project)
The City of San Diego
Project Information Details
Adams North Improv 1 (S)
(Design Build Project)
Print Page  
General Information
B22043 (Sewer Asset)
Replace approximately 2,609 LF (0.49 mi) of existing 6- & 8-inch vitrified clay (VC) and PVC sewer mains with new 8-inch PVC sewer mains. Rehab approximately 7,020 LF (1.33 mi) of existing 6-, and 8-inch VC sewer mains. Install approximately 430 LF (0.08 mi) of new 8-inch pipe. Abandon approximately 120 LF (0.02 mi) of existing 6-inch VC sewer main.
Sleiman, Alex
9
MID-CITY:NORMAL HEIGHTS
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $8,176,575
Design-Build Activity
(1) $5,296,000
(3) Partially Funded
To Be Selected
(1) Duration to be determined.
Additional Remarks
None
See B22044 for Water Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 04/01/2024