The City of San Diego Project Information Details
4182 60th St & 5973 Alta Mesa Wy Emer
(Emergency (Std, as-needed) Project)
The City of San Diego
Project Information Details
4182 60th St & 5973 Alta Mesa Wy Emer
(Emergency (Std, as-needed) Project)
Print Page  
General Information
B22052 (Storm Water Drainage Asset)
The scope of work shall include but not be limited to design and construction services to repair and/or replace approximately 300 feet of existing 18-inch corrugated metal pipe storm drain within private properties and slope
Choi, Jong
9
MID-CITY:EASTERN AREA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $3,201,232
Construction Activity
(1) $2,250,000
(3) Fully Funded
J.R. Filanc Construction Company, Inc.
(1) 13 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.