B22146 (Airport Asset)
This project provides for the roof replacement with induction welding Thermoplastic Polyolefin
roofing system with a 20 year Guarantee period. The project also includes; patching over
penetrations created from removed HVAC equipment, complete removal of existing roof
assembly, sheet metal and trim, storm drain piping specialties; in Building 1, approximately 16,300
square feet.
Shackelford, Kris
7
KEARNY MESA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $755,000
Construction Activity
(1) $612,000
(3) Fully Funded
To Be Selected
(1) 9 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.